Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Semi loses wheel, causes collision

No injuries in collision east of Sicamous involving transport trucks

Young Salmon Arm athletes gear up for the 2018 BC Winter Games

20 competitors across five events vying for the podium in Kamloops

Sicamous Eagles impress despite difficult season

It was not a banner season for the Sicamous Eagles, but there… Continue reading

Documentary features Salmon Arm cinema

Out of the Interior shines a spotlight on the Salmar Classic

ALR review may not be open-minded

Past agriculture minister Norm Letnick skeptical of NDP approach

Your Feb. 21 Morning Brief

Check out the top stories of the day in the Okanagan-Shuswap with Carmen Weld’s Black Press Morning Brief.

How to keep local news visible in your Facebook feed

Facebook has changed the news feed to emphasize personal connections. You might see less news.

Thief helps himself to cash register

Vernon business asking for public’s help to identify suspect

Slow speed head-on crash with police car

A vehicle crashed head-on into a police car in Kamloops this morning

BCHL Today: Merritt peaking at right time and Taylor signs with UNH Wildcats

BCHL Today is a (near) daily look at what’s going on around the league and the junior A world.

Day 100

Parkview Elementary student Myles Low shows off his hand-made eyewear celebrating the… Continue reading

Video: B.C. firefighters featured in quirky video

Oliver Fire Department posts video about their B.C. volunteer firefighter spring training seminar

OLYMPIC ROUNDUP: Two more medals push Canada into third place

A gold in ski cross and a bronze in bobsleigh as men’s hockey advances to the semis

Most Read