B.C. issues Trans Mountain pipeline permit update as premier heads to Ottawa

Ministry says 201 of 587 permit applications submitted to various permitting agencies are approved

B.C.’s government has issued a progress report on permits for the Trans Mountain pipeline expansion, just as Premier John Horgan readies to travel to Ottawa for a meeting on the controversial project.

The Energy, Mines and Petroleum Resources Ministry says the $7.4-billion project requires 1,187 provincial permits, many of which involve Indigenous consultations.

The ministry says in a statement that 587 permit applications have been submitted to various permitting agencies and of those, 201 have been approved and issued while another 386 are under review.

The report comes as Horgan denies that B.C. is delaying the permitting process, but his statements haven’t satisfied Alberta, the federal government or Kinder Morgan, the pipeline’s owner.

The company announced last week it is stopping essential spending on the project because of opposition and delays in British Columbia and it gave May 31 as a deadline for government action.

Prime Minister Justin Trudeau has summoned Horgan and Alberta Premier Rachel Notley to Ottawa for a meeting on Sunday to discuss the escalating pipeline feud.

READ MORE: ‘I dare you’: B.C. councillor calls out feds in pipeline dispute

READ MORE: B.C. blasted for Trans Mountain pipeline tactics

READ MORE: Oil-by-rail traffic rises as B.C. battles over Trans Mountain pipeline

Notley said this week Alberta is preparing to punish B.C. with legislation that could restrict the flow of oil to the West Coast, likely causing a spike in gasoline prices, which currently hover around $1.50 a litre in Metro Vancouver.

Notley also said Alberta is prepared to take over the pipeline.

The federal government approved the project, which would triple capacity of the pipeline running between Edmonton and Burnaby in 2016.

Trudeau has repeatedly said Trans Mountain is in the national interest and will get built.

B.C.’s Energy, Mines and Petroleum Resources Ministry said in a statement Friday that Kinder Morgan must still submit about 600 permits for the expansion.

It said the submitted permits must align with 37 conditions outlined in B.C.’s environmental certificate and the 157 conditions detailed in the National Energy Board’s approval.

Horgan said Friday that B.C. is heading to court to test its jurisdictional authority over the pipeline, but until then, the government is not holding up the expansion.

“We are not thwarting the project,” he said. “We are issuing permits as they ask for them.”

But the provincial government will continue to state its belief that the pipeline poses environmental and economic risks that are too great, Horgan added.

“I do believe we have a mandate to defend the coast,” he said. “I would also argue the premier of B.C. has an obligation at all times to stand up for the jurisdictional authority of provincial rights.”

The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

In photos: The 27th Annual Salmon Arm Roots and Blues Festival

Images from Friday evening and Saturday at the festival grounds.

Summerland cannabis shop receives approval in principle

Inspection now required before Green Gaia may sell cannabis

North Okanagan-Shuswap Liberal candidate responds to Trudeau ethics report

Prime Minister’s immediate response to commissioner’s findings appreciated

Shuswap tow truck operator sees high number of collisions this summer

Drivers encouraged to “loosen up behind the wheel, smarten up and read the road”

VIDEO: Langley Ribfest met with protesters

Groups that oppose the event for various reasons plan to be on site each of the three days.

Canadians killed in Afghanistan honoured during emotional dedication ceremony

One-hundred-fifty-eight Canadian soldiers died during the mission

It’s snow joke: Up to 30 cm of snow expected to fall in northeastern B.C.

Alaska Highway, Fort Nelson to be hit with August snowstorm, according to Environment Canada

‘I’m just absolutely disgusted’: Husband furious after B.C. Mountie’s killer gets day parole

Kenneth Fenton was sentenced to prison after he fatally struck Const. Sarah Beckett’s cruiser

Sea-to-Sky Gondola in B.C. likely out of commission until 2020

Sea to Sky Gondola carries between 1,500 and 3,000 people every day during the summer season

Helicopter-riding dog Mr. Bentley now featured on cans of new B.C.-made beer

Partial proceeds from every pack go to Children’s Wish

PHOTOS: Weapons seized at Portland right-wing rally, counterprotests

Not all who gathered Saturday were with right-wing groups or antifa

Retrieved body from Okanagan Lake identified as missing kayaker

Zygmunt Janiewicz had been missing since May and was recovered Aug. 10

Paddleboard festival coming soon to Kalamalka Lake

Wildfire smoke got in the way of last year’s event, but conditions look better this summer

Most Read