A checkpoint is seen at a bridge leading to the Unist’ot’en camp on a remote logging road near Houston, B.C., on January 17, 2019. A natural gas pipeline project has polarized many communities across northern British Columbia in a dispute a Wet’suwet’en elder says he hopes will be resolved through dialogue. Coastal GasLink is building the 670-kilometre pipeline from British Columbia’s northeast to Kitimat on the coast. The company has signed agreements with all 20 elected First Nation councils along its path, but the hereditary clan chiefs who are leaders under the traditional form of governance say the project has no authority without their consent.THE CANADIAN PRESS/Darryl Dyck

A checkpoint is seen at a bridge leading to the Unist’ot’en camp on a remote logging road near Houston, B.C., on January 17, 2019. A natural gas pipeline project has polarized many communities across northern British Columbia in a dispute a Wet’suwet’en elder says he hopes will be resolved through dialogue. Coastal GasLink is building the 670-kilometre pipeline from British Columbia’s northeast to Kitimat on the coast. The company has signed agreements with all 20 elected First Nation councils along its path, but the hereditary clan chiefs who are leaders under the traditional form of governance say the project has no authority without their consent.THE CANADIAN PRESS/Darryl Dyck

B.C. orders Coastal GasLink to stop pipeline construction near protected wetlands

The 670-kilometre pipeline is planned to transport natural gas from northeast B.C. to Kitimat

  • Jul. 8, 2020 1:45 p.m.

By Matt Simmons, Local Journalism Initiative reporter, The Narwhal

Coastal GasLink has been forced to stop pipeline construction near protected wetlands after an inspection by the B.C. Environmental Assessment Office found the company cleared areas without completing the required surveying and planning.

Coastal GasLink was issued two non-compliance orders in June and now has to complete the surveys before the project can proceed in the affected areas.

The 670-kilometre pipeline is planned to transport natural gas from northeast B.C. to Kitimat, for shipment to markets in Asia.

Wet’suwet’en Hereditary Chiefs served Coastal GasLink with an eviction notice on Jan. 4, starting a chain of events that led to RCMP enforcing a court-ordered injunction to arrest more than 80 protesters in February, including elders, chiefs and matriarchs. On June 5, charges against 22 Wet’suwet’en members and supporters were dropped and many others were never charged.

The Unist’ot’en and Gidimt’en Clans brought two wetlands areas of concern to the attention of the Environmental Assessment Office this spring. When inspection officers investigated, they found construction had begun in these areas prior to proper surveying and planning.

The assessment office then inspected the remainder of the pipeline route and found the company’s wetlands management plan had not been followed in any of the wetlands along the route designated “ecologically and socioeconomically important,” according to a news release from the Unist’ot’en (Dark House), of Wet’suwet’en Nation, on Monday.

Coastal GasLink produced its own wetlands management plan “and cannot claim ignorance of the requirements laid out within it,” Unist’ot’en said.

As part of that plan, and under Coastal GasLink’s environmental assessment certificate, the company is required to conduct surveys of these ecologically sensitive areas prior to clearing and develop site-specific plans for mitigating any adverse effects caused by construction or clearing.

B.C.’s Ministry of Environment and Climate Change Strategy declined an interview request but said in a statement that 42 wetlands areas are affected. The Unist’ot’en release says there are nearly 300 protected wetlands along the pipeline route and Coastal GasLink hasn’t developed site-specific mitigation plans for any of them. It adds that nearly 80 per cent of the pipeline right of way has already been cleared, affecting most of these protected wetlands.

The assessment office issued two non-compliance orders — one on June 16 for not taking measures to limit the damage done to wetlands, and the other on June 22 for proceeding with work to clear the sites for construction prior to conducting the required surveys.

Coastal GasLink must now cease construction within 30 metres of wetlands areas designated as socio-economically important until construction preparation surveys are completed and an expert in wetlands conservation, on behalf of the company, has visited each site to identify options for minimizing the harm caused to the area during construction.

The orders are accompanied by another non-compliance order issued on June 16 due to workers’ lack of efforts to mitigate harm to whitebark pine, an endangered species in Canada. Last year, the company faced another order after initiating work prior to notifying trapline owners in the area around Houston.

READ MORE: RCMP patrol of smokehouse sparks concerns by Wet’suwet’en hereditary leader

Jason Slade, technical adviser to Unist’ot’en, says the Wet’suwet’en have been asking Coastal GasLink for months for site-specific plans regarding clearing and construction in wetlands.

The company said in a statement it does have a plan, but the assessment was not compliant with the plan.

Coastal GasLink said it is complying with the stop-work order for the identified sites.

“Environmental protection is a top priority for us,” spokesperson Suzanne Wilton told Black Press, adding that work has already begun under the enforcement orders to survey and report on the damage. She expects the company will be back in compliance by the end of July.

While Coastal GasLink completes its wetlands plans, work continues in other areas where work camps are being built and populated in preparation for laying the pipeline this summer. As of May 31, roughly 77 per cent of the route had been cleared and installation had started in Kitimat earlier this month. The company said it does not expect the stop-work order to have an overall impact on the project schedule.

Pipeline materials are stored in Houston, but Sleydo’ (Molly Wickham), a Gidimt’en spokesperson, says she hasn’t seen much work happening on Gidimt’en or Dark House territory. In Vanderhoof, about two hours away, it’s a different story. Construction on a 900-bed work camp is well underway.

In May, nine Wet’suwet’en hereditary chiefs signed a memorandum of understanding with the provincial and federal governments to work toward affirming Wet’suwet’en rights and title. But it doesn’t mean the hereditary chiefs have changed their stance on Coastal GasLink.

“We are still in opposition,” she says emphatically. “People should know that. The eviction order stands. And we’ll enforce that eviction order.”

READ MORE: Coastal GasLink will consult with health authorities before construction recommences

In a statement, the B.C. Ministry of Indigenous Relations and Reconciliation said the memorandum of understanding is a first step toward resolving “difficult and complicated issues” around Wet’suwet’en rights and title.

“By resolving these issues, we can avoid the kind of conflicts we’ve seen on the land, and work together for the benefit of all people who live in the region,” the statement said.

The ministry acknowledged that “at the time the MOU was reached, all parties at the table recognized that the differences relating to the Coastal GasLink project remain. That has not changed.”

With files from Thom Barker


Like us on Facebook and follow us on Twitter.

Coastal GasLink

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

An air ambulance carrying a suspected injured longboarder takes off from a Spallumcheen property near Otter Lake Road Saturday, April 17. (Richard Breaks photo)
Suspected longboard crash in Spallumcheen sends individual to hospital via air ambulance

Accident involved a North Okanagan man in his late 20s on Otter Lake Road in the township

Vernon Vipers forward Ryan Shostak (centre) fends off a check from Salmon Arm defenceman to get a close-in scoring attempt on Silverbacks goalie Owen Say during Vernon’s 3-2 B.C. Hockey League pod play shootout victory Saturday, April 17, at Kal Tire Place. (Lisa Mazurek - Vernon Vipers photography)
Vernon Vipers use shootout to subdue Salmon Arm

Snakes score 3-2 B.C. Hockey League pod play win at Kal Tire Place

A GoFundMe page has been launched for a Vernon man whose BX orchard property home off Pleasant Valley Road near Stickle Road was totally destroyed in a fire Saturday, April 17. (Brendan Shykora - Morning Star)
Fundraising campaign launched for Vernon man who lost home to fire

A GoFundMe page has been started by family; man taken to hospital with injuries from fire

Armaan Dhaliwal hands a cheque for $500 to Shuswap Hospital Foundation president Angie Spencer as his proud grandparents Gordie and Nancy Dhaliwal watch on Friday, April 16. (Jim Elliot/Salmon Arm Observer)
Salmon Arm boy’s samosa sales benefit hospital foundation

Armaan Dhaliwal was able to give the Shuswap Hospital Foundation a $500 donation

School District 83 trustees are expected to be discussing the current Long Range Facilities Plan options at the April 20 school board meeting. (File photo)
Letter: Let the people have their say on Salmon Arm school options

Parent encourages School District 83 board to hold off on making a decision

Vancouver resident Beryl Pye was witness to a “concerning,” spontaneous dance party that spread throughout social groups at Kitsilano Beach on April 16. (Screen grab/Beryl Pye)
VIDEO: Dance party erupts at Vancouver’s Kitsilano Beach to the dismay of onlookers

‘It was a complete disregard for current COVID-19 public health orders,’ says Vancouver resident Beryl Pye

A North Okanagan man in his late 20s was flown to hospital by air ambulance Saturday, April 17, shortly after 6:30 p.m. after allegedly crashing on his longboard on a Spallumcheen roadway. (File photo)
Suspected longboard crash in Okanagan sends individual to hospital via air ambulance

Accident involved a North Okanagan man in his late 20s on Otter Lake Road in Spallumcheen

Deputy Prime Minister and Minister of Finance Chrystia Freeland responds to a question during Question Period in the House of Commons Tuesday December 8, 2020 in Ottawa. The stage is set for arguably the most important federal budget in recent memory, as the Liberal government prepares to unveil its plan for Canada’s post-pandemic recovery even as a third wave of COVID-19 rages across the country. THE CANADIAN PRESS/Adrian Wyld
Election reticence expected to temper political battle over federal budget

Opposition parties have laid out their own demands in the weeks leading up to the budget

A Kelowna Pride Festival 2019 participant holds up a flag. (Kelowna Pride Society)
Kelowna Pride, RCMP continue to work on ‘Safe Place Program’

A new committee has been formed to refine the ‘Safe Place Program’ created by the Kelowna RCMP

Coldstream Fire Department crews stationed at Kal Lake Provincial Park parking lot on Cosens Bay Road on Sunday, April 18, after a car went over a cliff in the area. (Roger Knox - Morning Star)
Driver escapes after car goes over North Okanagan cliff

The driver has been transported to hospital with unspecified injuries

A strange odour at a West Kelowna apartment building prompted the evacuation of 150 residents on Sunday morning, April 18. (Aaron Hemens - Capital News)
Strange smell at West Kelowna apartment prompts evacuation of 150 residents, pets

150 residents ordered evacuated from a West Kelowna apartment building early Sunday morning

This is what’s left of a truck that caught fire at Pyramid Provincial Park off Highway 97 near Summerland Saturday night. (Monique Tamminga Western News)
Photo Gallery: Truck gutted by fire at popular Okanagan park, trees saved

Just a metal shell of what once was a pick up truck is left at the scene

A syringe is loaded with COVID-19 vaccine at a vaccination clinic run by Vancouver Coastal Health, in Richmond, B.C., Saturday, April 10, 2021. THE CANADIAN PRESS/Jonathan Hayward
B.C. to open up COVID vaccine registration to all B.C. residents 18+ in April

Registration does not equate to being able to book an appointment

Most Read