Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepancies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Chilliwack on the map for Salmon Arm Roots and Blues

Canadian music legends confirmed for 28th annual music festival

CSRD green light’s Blind Bay cannabis store, provincial approval required

Public survey shows 55 per cent in favour, 42 per cent opposed to proposed outlet

Driver of speedboat in fatal Shuswap Lake houseboat collision denied parole

Court says Leon Reinbrecht unwilling to accept culpability for “reckless, thrill-seeking behaviour”

Mould mitigation at Sicamous elementary school near complete

School District #83 superintendent says health concerns have been resolved

Snowy softball in Sicamous

The 2020 snowpitch tournament took place at Finlayson Park on Jan. 18 and 19.

VIDEO: Soldiers trade rifles for snow shovels to help dig out St. John’s

A state of emergency is set to extend into a fifth day

Warm ‘blob’ could be behind mass starvation of North Pacific seabirds: study

Unprecedented death toll raises red flag for North American marine ecosystems

North Okanagan woman pleas for return of stolen scooter

‘It’s been another kick in the teeth… how do you get ahead and keep your head above water?’

Police search for owner of another icy sailboat on Okanagan Lake

The frozen vessel was spotted near the 800 block of Manhattan Drive in Kelowna

Volunteer spends hundreds of hours restoring piece of railway history

Revelstoke Railway Museum now home to an authentic Kalamazzo No. 2 Section Handcar

Future of Penticton francophone school secured following funding announcement

$11.5M in funding means École Entre-lacs now independently owned and operated

ICBC to bring in ranking system for collision, glass repair shops

Change comes after the much-maligned auto insurer has faced criticism for sky-high premiums

City of Vernon to redirect reclaimed water into Okanagan Lake

MacKay Reservoir nears capacity; city to reflow water into lake near Kin Beach

Most Read