Cost to twin Trans Mountain pipeline now $1.9B higher, Kinder Morgan says

Financial documents now say the company expects a $9.3-billion price tag

Kinder Morgan Canada documents say expanding the Trans Mountain pipeline will cost the federal government another $1.9 billion beyond the company’s original construction estimate and will take another full year to complete.

The figure is included in documents Kinder Morgan Canada filed Tuesday with the United States Security and Exchange Commission related to the company’s plan to sell the pipeline to the Canadian government for $4.5 billion.

READ MORE: B.C., Alberta clash as Kinder Morgan suspends Trans Mountain work

READ MORE: How will Ottawa finish a pipeline Kinder Morgan couldn’t?

READ MORE: Kinder Morgan protest in Delta ends peacefully

Kinder Morgan has long said it would cost $7.4 billion to build a second pipeline parallel to the first in order to triple its capacity, but the financial documents now say the company expects a $9.3-billion price tag.

The documents also suggest construction won’t be done until December 2021 — a full year beyond the last projection of December 2020.

Finance Minister Bill Morneau has been reluctant to discuss how much more it will cost to build the pipeline while the deal is still being finalized, and the closing date for that deal is now being pushed back well into the fall.

The documents also say shareholders will meet Aug. 30 in Calgary to vote on the proposed sale.

The Canadian Press


Like us on Facebook and follow us on Twitter.

Just Posted

A 64-year-old dies while mountain biking in Blind Bay

Shuswap Search and Rescue came assist first responders at the scene

City looks at extending public transit to evenings, Sundays

Salmon Arm council to consider expanding services, sharing costs with BC Transit

Plans rolling along for Silver Creek bike trail

CSRD expects construction of 3.65-kilometre path to begin in September 2019

Boil water notice lifted for residents on Sunnybrae system

Recent testing finds turbidity at acceptable levels

City seeks public approval to borrow $845,000 for airport runway project

Salmon Arm residents have until June 24 to voice opposition to borrowing bylaw

B.C.’s fight to regulate bitumen through pipelines to go to Canada’s top court

BC Appeal Court judges found B.C. cannot restrict bitumen flow along Trans Mountain pipeline

Friend of accused Kelowna murderer takes the stand

Elrich Dyck’s testimony continued Friday with details from the night Chris Ausman was killed

Osprey nest in downtown Salmon Arm will remain until new year

The powerlines around the nest have been de-energized so the birds can stay until spring

Crews respond to smoke at Penticton thrift store

The rooftop A/C unit began filling the building with smoke, prompting them to evacuate

Housing provided for women and children fleeing violence in Penticton

Announcement on Friday is part of a provincewide initiative to construct additional housing.

People’s Party of Canada leader talks B.C. trade to Penticton supporters

Maxime Bernier, head of the new federal political party, spoke at Time Winery on Friday

Princeton RCMP recover stolen homework and save the grade

It’s a slightly better excuse than “the dog ate my homework.” Earlier… Continue reading

New Summerland distillery has received recognition

Alchemist Distiller won audience choice award at recent competition

Scheer says it would take Conservatives five years to balance budget

Scheeraccused the Liberal government of spending $79.5 billion of previously unbudgeted funds

Most Read