Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

PHOTOS: PeeWee Silverbacks finish season with 22 game win streak

The team has gone undefeated since November last year

Word on the street: What is your favourite pie-related memory?

With the 24th-annual Best of the Shuswap Pie Baking Contest taking place… Continue reading

Fiery collision involving truck closes Highway 1 at Three Valley Gap

Drivers should expect major delays and congestion; estimated time of re-opening is 2 p.m.

Spectators asked to be on best behaviour at Shuswap school sporting events

Policy asks that spectators make positive comments remain silent

Governor general says multiple solutions needed for ‘complicated’ overdose issue

Julie Payette met at a fire hall with firefighters and police officers as well as politicians and health experts

Violent ends to past Indigenous protests haunt Trudeau government

Trudeau adopted a more assertive tone Friday, insisting the barricade must come down

Kelowna Firefighters douse suspicious hedge fire

A 30’ section of cedar hedge burned prompting an RCMP investigation.

Kelowna RCMP make arrest in fatal stabbing of 16-year-old Elijah Beauregard

An 18-year-old woman is in police custody facing a manslughter charge.

HIGHLIGHTS: Day one and two at the 2020 BC Winter Games

Athletes had sunny – but cold – weather to work with in Fort St. John

B.C. money laundering inquiry to begin amid hopes for answers, accountability

Eby argued that most B.C. residents already know the previous government, at best, turned a blind eye

Most Read