Shovels could be in the ground on Trans Mountain by September, CEO says

Ian Anderson points to weeks likely required for NEB to reinstate 2016 regulatory record

The CEO of the Crown corporation building the Trans Mountain pipeline expansion says shovels could be in the ground by September following cabinet approval Tuesday of the long-delayed project.

Oil could be flowing in new segments of the pipeline between Edmonton and the West Coast by mid-2022, Ian Anderson said, about one year later than the timeline envisioned last August when the Federal Court of Appeal quashed its regulatory approval and halted all fieldwork.

“We’re excited, our shippers are excited and the communities we touch are excited along the pipeline corridor,” said the CEO of Trans Mountain Corp. during a conference call Wednesday.

“We’re confident now that our project will meet every standard, every regulation, every test and reflect the values and priorities and principles that we all care for as Canadians.”

The National Energy Board is being asked to reinstate the record from the previous regulatory proceeding in 2016 so that the project can be brought back to the same state of construction readiness as last summer, Anderson said, a process expected to take some weeks.

He said the fact the federal government owns the pipeline won’t change or hurry the process.

Two re-routing requests are still to be decided, he said, including one involving B.C.’s Coldwater reserve, although those processes aren’t expected to affect the timeline.

He said contractors are being mobilized, pipe is being stockpiled in yards in Alberta and B.C. and the Burnaby terminal on the West Coast is being made ready so that construction work can begin there as soon as permitted.

Anderson said there is no update on the last estimated project cost of $7.4 billion, while conceding that “time is money.”

Earlier Wednesday, Finance Minister Bill Morneau told a Calgary business audience the best way to convince a skeptical oilpatch that the expansion will actually be built is to go ahead and build it.

“What we said yesterday was that we renewed that (pipeline) approval,” Morneau told reporters.

“What’s happening today is we’re back at work. The re-permitting is happening starting today. We are going to get work going this construction season. I want people in Alberta and people across the country to know that intent is real.”

Last August, the Federal Court of Appeal ripped up the original federal approval of the 590,000-barrel-per-day expansion, citing incomplete Indigenous consultations and a faulty environmental review.

Dan Healing, The Canadian Press

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Spectators asked to be on best behaviour at Shuswap school sporting events

Policy asks that spectators make positive comments remain silent

Rezoning to accommodate Ashley Furniture store highlights traffic concerns

Developer would like covenant requiring traffic study to exclude furniture store site

Knights of Columbus step up for Shuswap community groups

Organizations from Shuswap, Thompson regions receive $15,000

Silverbacks forward receives BCHL Community Hero Award

Award presentation for Coalson Wolford to take place Sunday, Feb. 23

Deaths on popular Shuswap trail ruled accidental

Trail to remain closed until recommended works completed

VIDEO: B.C. senior recalls ‘crazy’ wartime decision to grab bear cub from den

Henry Martens – now 96 – says he was lucky to be alive after youthful decision to enter a bear’s den

Eyes on police after Trudeau orders blockades torn down, injunctions enforced

The RCMP in B.C. have sent a letter to the traditional leaders of the Wet’suwet’en Nation

B.C. massage therapist suspended following allegations of sexual misconduct

While suspended, Leonard Krekic is not entitled to practice as an RMT in B.C.

Gas drops below a dollar per litre in Penticton

Two stores in Penticton have gas below a dollar.

Pawsative Pups: You have a new puppy, now what?

Lisa Davies is a new columnist for Black Press who writes about dog training

Loans or gifts? Judge rules woman must pay B.C. man back $7K

B.C. judge rules that woman must pay back more than $7,000 in advanced funds to man

VIDEO: Outpouring of worldwide support for bullied Australian boy

Australian actor Hugh Jackman said ‘you are stronger than you know, mate’

Sewer service planned for South Okanagan community of Kaleden

Regional District of Okanagan Similkameen plans to extend Okanagan Falls system into Kaleden

‘A horror show:’ Ex-employee shares experience at problematic Chilliwack seniors’ home

Workers are paid below industry standard at all Retirement Concepts facilities

Most Read