Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Late last year, officials warned that a federal spending spree to repair crumbling roads and water systems could take three years longer than expected to complete, based on internal documents outlining issues with the first tranche of cash in the federal government’s infrastructure program.

The federal government had originally hoped to have cities and provinces complete $5.4 billion in transit and water system work by this March, but quickly realized that more time was needed.

A “secret” fall briefing note to Infrastructure Minister Amarjeet Sohi, obtained by The Canadian Press through the Access to Information Act, says delays hampered a large number of construction projects, requiring that the deadline be extended as far as March 2021.

The heavily blacked-out document predicted the majority of water and transit projects “would require extensions not only for a third year, but beyond into a fourth year (i.e. 2019-20) and fifth year (i.e. 2020-21),” referencing the federal fiscal years in brackets.

Sohi agreed to a blanket deadline extension to March 2020, turning what was to be a two-year stimulus program into a four-year plan.

He said the decision to grant extra time to 2020, instead of 2021, was based on the expected cash flow for projects and the ability for construction companies to handle all the extra work.

“This is not about that projects are being delayed, it’s about taking a little longer to complete those projects or taking a little longer to have the buses manufactured because of construction and manufacturing capacity,” Sohi said in an interview from Edmonton.

“From our perspective, we made a commitment to build and rebuild infrastructure and focus on the repairs in phase 1 and … we are achieving the results we intended to achieve, but we also want to give flexibility.”

As of Friday, the federal government had approved more than 3,400 water and transit projects with a combined federal contribution valued at almost $4.2 billion. Of that money, federal coffers had only doled out about $175.6 million to date, based on figures available on the Infrastructure Canada website.

Federal dollars flow once cities and provinces submit receipts for reimbursement, often creating a lag between when work takes place and when the federal money is spent.

In some cases, the federal government won’t receive receipts until a project is completely done. In other cases, projects are delayed because of labour strife, bad weather or other factors beyond Ottawa’s control.

The government says 793 projects representing about $1.8 billion in federal contributions have been granted individual extensions from Sohi. Between those extensions, and delays in filing expense claims, federal officials last year decided to shift more than $2 billion in planned spending to future years.

Provincial and municipal officials say that the time needed to go through the funding approval process contributed to the delays.

Having officials vet the details of each proposal before getting federal approval for funding meant some cities put off breaking ground until they knew federal funding would come their way.

“We heard loud and clear from some municipalities that they were struggling to meet two pieces of criteria: timeline requirements and a provision that would require municipalities to incur 60 per cent of their costs by March 31st, 2018,” said Alex Benac, a spokesman for Ontario Infrastructure Minister Bob Chiarelli.

The extra time and removal of the local spending requirement, which Chiarelli asked for in September, has given cities “much-needed time to get shovels in the ground and keep their projects on track according to a more generous, achievable timeline,” Benac said.

Federal and provincial officials say the lessons learned from the first phase of the program will be used in designing the second phase.

Both sides want funding agreements for the second, longer and more lucrative phase of infrastructure spending signed by March.

Jordan Press, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

District of Sicamous and Federal government come to terms on biomass heater grant

Once completed the project could heat arena elementary school and more using wood waste

City to renew agreement with Shaw for public Wi-Fi access

Wireless networking hotspots will continue to be available at Salmon Arm parks and facilities

Longtime Shuswap school bus driver takes one last ride

Kathy Keam drove students on the same bus route for 38 years

Dogs called heroes in Blind Bay residential blaze

Homeonwers safe but one pet missing, another confirmed dead following fire

Semi in ditch slows Highway 97 traffic north of Vernon

The accident occurred near Irish Creek Road Thursday, Jan. 17

B.C. opioid crisis to get same world-renowned treatment approach as HIV/AIDS

A program that focuses on treatment as prevention will roll out Jan. 17

Olympian snowboarder Max Parrot diagnosed with Hodgkin’s lymphoma

Each year in Canada, approximately 900 people are diagnosed with Hodgkin’s lymphoma

‘Prince of Pot’ Marc Emery accused of sexual assault, harassment

Emery denied the allegations, but a Toronto woman says she is not the only one speaking out

Vancouver Island photographer makes National Geographic’s 2018 elite

Rare double honour for Marston from the 36 best Your Shots out of nearly 19,000 photos

Ex-Liberal candidate in Burnaby, B.C., says volunteer wrote controversial post

Karen Wang dropped out following online post singling out NDP Leader Jagmeet Singh’s ethnicity

Asteroids are smacking Earth twice as often as before

The team counted 29 craters that were no older than 290 million years

Canada’s arrest of Huawei exec an act of ‘backstabbing,’ Chinese ambassador says

China has called Canada’s arrest of Huawei chief financial officer Meng Wanzhou ‘politically motivated’

Remorse high for Vernon man sentenced for car surfing death

Driver of car that killed friend who was car surfing gets nine months in jail

Shuswap curlers hit the ice in Salmon Arm Curling Club’s Stick Bonspiel

Annual event enters 12th year, sees 24 teams enter

Most Read