Work on replacement of the Solsqua-Sicamous bridge is underway. (File Photo)

Work on replacement of the Solsqua-Sicamous bridge is underway. (File Photo)

Solsqua-Sicamous Bridge work on pace for June 2021 completion

Replacement of the 100-year-old span began last August.

If work on the bridge replacement project continues as planned, drivers can expect to be crossing the Eagle River using a new Solsqua-Sicamous Bridge by June.

An update delivered to Sicamous’ council at its Feb. 24 meeting by Brandon Barker from ISL Engineering suggested about 62 per cent of the project remained unfinished, leaving around three months of work to go.

The report from the engineering firm stated that pre-cast bridge girders for the new span were on site and ready for placement. There were still several inspections the bridge must pass before the completion of the project. Sicamous operations manager Joe McCulloch told council he was happy with the progress on the project and that he believed the new bridge will be finished by its May 31 deadline, and within its estimated budget.

Read More: Sicamous receives $4.8 million in grant funding for infrastructure projects

Read More: Bridge replacement to get underway in Sicamous

Once the new bridge is finished, removal of the old bridge and its pilings is expected to continue until the end of 2021.

Full extraction of the old bridge’s pilings was not part of the original contract, but it is being required by Transport Canada. According to ISL’s report to council, the contractor working on the bridge replacement thinks that full removal of the old pilings can be accomplished for about $33,000.

According to Barker, removal of the old bridge piling and other in-stream works will likely have to wait until November or December 2021. The delay is because work in fish-bearing streams are only permitted by the government at certain times of year.

Read More: Shuswap auto recycler breaks out of Rust Valley for Backroad Truckers

Read More: New video promotes Salmon Arm staples of agriculture, food production

Construction cost for the bridge was estimated at $4,556,949. The district received a $4.5 million federal government grant in 2018. For related professional services, including engineering, the cost was estimated at $1,286,669. With some variability on the actual costs to complete the project, the final total cost is estimated to be up to $5.84 million.

Along with the federal grant, a financial report to council anticipated $720,000 would be spent from the district’s bridge reserves, as well as $449,936 from the community works fund.

Mayor Terry Rysz compared the current progress to the state of things eight or nine years ago, when it was clear the nearly 100-year-old the bridge would need to be replaced soon but no one was sure how they would pay for it.



jim.elliot@saobserver.net

Like us on Facebook and follow us on Twitter

Sicamous

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

B.C. wineries are open for indoor tasting despite new provincial health regulations. Photo- 
50th Parallel Winery, Instagram.
Indoor wine tastings still allowed in B.C., not considered a ‘social gathering’

“Tasting is really just part of the retail experience. The analogy I use is you wouldn’t buy a pair of pants without trying them on.”

Scotch Creek residents on the Saratoga water system will be without water for most of April 14 as the Columbia Shuswap Regional works on water system upgrades. (File photo)
Water system shutdown planned for Scotch Creek

Residents on Saratoga system encouraged to store water in case shutdown is longer than expected

Developer Bill Laird has applied to the city to have the two-acre parcel (outlined in yellow) behind the Westgate Mall, which is already out of the Agricultural Land Reserve, ready for development by having it included within the city’s Urban Containment Boundary and redesignated in the official community plan. (City of Salmon Arm image)
Plan to prepare field behind Westgate Mall for development gets initial OK

Proposal to expand urban containment boundary forwarded to council’s April 12 meeting

Mainly clear and sunny skies are expected for the Okanagan-Shuswap region this week. (Maxpixels photo)
Warm, sunny week ahead in Okanagan-Shuswap

Daytime highs will reach the low 20s with mainly clear skies this week

Janice Cannon, right, of Little Red Hen Artisan Bakery boxes up a selection of items for a customer at last year’s Downtown Salmon Arm Farmer’s Market. The Salmon Arm bakery is returning for this year’s market. (File photo)
Young vendors sought for Downtown Salmon Arm Farmer’s Market opening

Shuswap Food Action Society seeking small appliances, kitchenware for SAFE Society

Burnaby MLA Raj Chouhan presides as Speaker of the B.C. legislature, which opened it spring session April 12 with a speech from the throne. THE CANADIAN PRESS
B.C. NDP promises more health care spending, business support in 2021 budget

John Horgan government to ‘carefully return to balanced budgets’

North Cowichan councillor Tek Manhas did not violate the municipality’s code of conduct by posting a sexist meme on Facebook, council concludes. (File photo)
B.C. municipality to take no action against councillor who posted sexist meme

Tek Manhas’s meme doesn’t violate North Cowichan council’s code of conduct, municipality concludes

The former Summerland Asset Development Initiative building on Prairie Valley Road in Summerland was suggested as the site for a temporary transitional housing facility for the community. However, Summerland council has rejected this proposal. (John Arendt - Summerland Review)
Summerland council rejects transitional housing facility

Concerns raised about short timeline and condition of municipally-owned building

Shayla, an 8-pound black and grey Havanese, was stolen from outside a store on Banks Road on Saturday. (Contributed)
Stolen pup located, Kelowna RCMP confirms

Mounties said on April 12 that Shayla, the 8-pound, black and grey Havanese dog, has been located safe and sound

Penticton Vees continue their winning streak carrying a 5-0 win title as of Sunday night's hockey action. (Cherie Morgan/Cherie Morgan Photography)
Penticton Vees continue winning streak

Sunday night’s 6-1 win has them with five in a row since the start of the season

A sign on a shop window indicates the store is closed in Ottawa, Monday March 23, 2020. The Canadian Federation of Independent Business is raising its estimate for the number of businesses that are considering the possibility of closing permanently. THE CANADIAN PRESS/Adrian Wyld
Small business struggling amid COVID-19 pandemic looks for aid in Liberals’ budget

President Dan Kelly said it is crucial to maintain programs to help businesses to the other side of the pandemic

The National Security and Intelligence Committee of Parliamentarians says that includes attempts to steal Canadian research on COVID-19 and vaccines, and sow misinformation. (AP Photo/Esteban Felix)
Intelligence committee warns China, Russia targeting Canadian COVID-19 research

Committee also found that the terrorist threat to Canada has shifted since its last such assessment

Parliament Hill is viewed below a Canada flag in Gatineau, Quebec, Friday, Sept. 18, 2020. A new poll suggests most Canadians are feeling more grateful for what they have in 2020 as a result of COVID-19 pandemic.THE CANADIAN PRESS/Sean Kilpatrick
Canada’s greenhouse gas emissions increased slightly in 2019: report

2019 report shows Canada emitted about one million tonnes more of these gases than the previous year

A car sheared a Hydro pole and the driver was pinned by a fence pole on 43rd Avenue Saturday, April 10. (Carmen Jaster photo)
Suspected impaired driver ‘lucky to be alive’ after crash in Vernon yard

Impaired driving investigation underway after driver shears Hydro pole and narrowly misses being impaled

Most Read